MVHS Community Hub
A new home for the community, now under construction
Into vertical construction
Bulk excavation is complete, and the basement retention works have been inspected with Regulation 126 compliance issued by the consultants. The project is progressing with proactive risk management.
- Basement retention completed: an essential foundation milestone.
- Bulk excavation finished on time under challenging conditions.
- Community first: clean roads and footpaths, upgraded nature strips and compliant stormwater measures.
- Constructive collaboration with the Conyers Street community, childcare operators and local businesses.
- Design rigour: transparent tracking of design updates and the permit secured despite evolving requirements.
- Safety & quality: zero incidents and no QA non-compliances this period.
- Target budget
- $5.2M ex GST
- Retention works
- ~98% complete
- Lifts delivered
- Expected June 2026
Financial snapshot
An expected over-run of about $150k is being offset by procurement gains of about $120k to date (ex GST). Monthly cashflow from December to May ranges from about $90k to $520k as works move into services and the superstructure.
Support the HubWho's building it
- Gudbuilt CivilRetention · ~98% complete
- Direct LiftsLifts · in manufacture
- Time PlumbingHydraulics & civil drainage
- D and B Mechanical ServicesMechanical · recommended
- Rajah ElectricsElectrical · recommended
- Davmar TRT ContractorsDincel walls · recommended
- JOYAReinforced blockwork · negotiating
- ScaffrightScaffolding · negotiating
Construction program
- Civil drainage, underground tanks and detailed excavation
- Lift pit construction, foundations and columns
- Partial scaffolding to the stairs area
- Dincel wall shop drawings, installation and concreting
- Slab on ground; formwork for the suspended ground floor slab
What's next
- Post-tensioned slab works from mid-January 2026
- Final awards for mechanical, electrical, Dincel walls, blockwork and scaffolding
- Continued design coordination and community updates
Help build the Hub
Sponsor five concrete blocks for $100, or one of the items below. Thank you to our community for your continued support.
| Item | Area | Price | Needed | Amount |
|---|---|---|---|---|
| Concrete blocks (5) | Entire building | $100 | Any | From $100 |
| Mirrors & other accessories | Sanitary fittings | $2,500 | 1 | $2,500 |
| Tapware (total) | Sanitary fittings | $3,000 | 1 | $3,000 |
| Urinals | Sanitary fittings | $2,100 each | 2 | $4,200 |
| Water closets (WC) | Sanitary fittings | $750 each | 10 | $7,500 |
| Toilet partitions | Sanitary fittings | $8,000 | 1 | $8,000 |
| Landscaping, pots etc. | Landscaping | $8,000 | 1 | $8,000 |
| Roller doors (automatic) | Car park | $8,500 | 1 | $8,500 |
| Timber doors & hardware | Hall | $10,000 | 1 | $10,000 |
| Art display: culture | Entrance | $12,000 | 1 | $12,000 |
| Green wall | Entrance | $12,000 | 1 | $12,000 |
| Fantech fans | Entire building | $15,000 | 1 | $15,000 |
| Wash hand basins | Sanitary fittings | $1,450 each | 10 | $14,500 |
| Other lighting, including LED, exit & emergency | Entire building | $15,000 | 1 | $15,000 |
| Main entrance glass door & panel | Entrance | $15,000 | 1 | $15,000 |
| TV & audio visual | Hall | $15,000 | 1 | $15,000 |
| Shop signage panels | Shops | $15,000 | 1 | $15,000 |
| Building signage | Front of building | $15,000 | 1 | $15,000 |
| Furniture & office equipment | Entire building | $15,000 | 1 | $15,000 |
| Joinery: reception & kitchenette | Kitchenette | $17,000 | 1 | $17,000 |
| Skylight | Hall | $17,500 | 1 | $17,500 |
| Metal work: car park grills | Car park | $28,000 | 1 | $28,000 |
| Ornamental lighting, open office area | Hall | $30,000 | 1 | $30,000 |
| Roller shutters: front & shops | Shops | $32,000 | 1 | $32,000 |
| Aluminium windows & glazing | Hall | $32,500 | 1 | $32,500 |
| Solar panels | Entire building | $35,000 | 1 | $35,000 |
| Doors & shop glazing | Shops | $35,000 | 1 | $35,000 |
| Data server & sound | Hall | $35,000 | 1 | $35,000 |
| Open office area: timber flooring | Hall | $38,500 | 1 | $38,500 |
| Fan coil units & cassettes | Hall | $46,500 | 1 | $46,500 |
| Aluminium doors, standard | Hall | $52,000 | 1 | $52,000 |
| Tiling (all areas) | Hall | $65,000 | 1 | $65,000 |
| Dismantlable stage | Hall | $65,000 | 1 | $65,000 |
| Passenger lift, 630 kg, 8 passengers | Entire building | $86,000 | 1 | $86,000 |
| Complete roofing (Colorbond Trimdek) | Entire building | $90,000 | 1 | $90,000 |
| Total for the items above | $900,200 | |||