A new home for the community, now under construction

Progress update · as of 21 December 2025

Into vertical construction

Bulk excavation is complete, and the basement retention works have been inspected with Regulation 126 compliance issued by the consultants. The project is progressing with proactive risk management.

  • Basement retention completed: an essential foundation milestone.
  • Bulk excavation finished on time under challenging conditions.
  • Community first: clean roads and footpaths, upgraded nature strips and compliant stormwater measures.
  • Constructive collaboration with the Conyers Street community, childcare operators and local businesses.
  • Design rigour: transparent tracking of design updates and the permit secured despite evolving requirements.
  • Safety & quality: zero incidents and no QA non-compliances this period.
Target budget
$5.2M ex GST
Retention works
~98% complete
Lifts delivered
Expected June 2026

Financial snapshot

An expected over-run of about $150k is being offset by procurement gains of about $120k to date (ex GST). Monthly cashflow from December to May ranges from about $90k to $520k as works move into services and the superstructure.

Support the Hub
Contracts & key trades

Who's building it

  • Gudbuilt CivilRetention · ~98% complete
  • Direct LiftsLifts · in manufacture
  • Time PlumbingHydraulics & civil drainage
  • D and B Mechanical ServicesMechanical · recommended
  • Rajah ElectricsElectrical · recommended
  • Davmar TRT ContractorsDincel walls · recommended
  • JOYAReinforced blockwork · negotiating
  • ScaffrightScaffolding · negotiating
December 2025 – 15 February 2026

Construction program

  • Civil drainage, underground tanks and detailed excavation
  • Lift pit construction, foundations and columns
  • Partial scaffolding to the stairs area
  • Dincel wall shop drawings, installation and concreting
  • Slab on ground; formwork for the suspended ground floor slab

What's next

  • Post-tensioned slab works from mid-January 2026
  • Final awards for mechanical, electrical, Dincel walls, blockwork and scaffolding
  • Continued design coordination and community updates